The FAT is the last point at which a fault costs hours rather than days. Everything is on the bench, the programmer is in the building, and a spare part is a drawer away. The protocol is written from the FDS, so that passing the FAT means the system does what the FDS says, and any gap between them is found here rather than on site.

Do you need this one?

Every panel that leaves your works. The cost of a witnessed FAT is always less than the cost of finding the same fault during a site shutdown.

What is in it

  1. 01Scope and references
  2. 02Entry criteria
  3. 03Test environment and simulation
  4. 04Documentation verification
  5. 05Visual and mechanical inspection
  6. 06Power up and electrical tests
  7. 07I/O verification, point by point
  8. 08Functional tests
  9. 09Interlock and safety tests
  10. 10Alarm tests
  11. 11Communications tests
  12. 12Failure mode tests
  13. 13Punch list
  14. 14Acceptance and sign-off

Written by

Control systems engineer

Approved by

Client witness, and project manager

Written against

  • IEC 62381 for automation system acceptance testing

Preview

FAT-Protocol.md
# Factory Acceptance Test Protocol
## {{PROJECT_NAME}}

| | |
|---|---|
| **Document title** | Factory Acceptance Test Protocol (FAT) |
| **Document number** | {{DOC_NO}} |
| **Revision** | {{REV}} |
| **Date** | {{DATE}} |
| **Project** | {{PROJECT_NAME}} |
| **Client** | {{CLIENT}} |
| **Prepared by** | {{AUTHOR}}, {{COMPANY}} |

### Revision history

| Rev | Date | Description | Author | Approved |
|---|---|---|---|---|
| 0 | {{DATE}} | First issue | {{AUTHOR}} | |
| | | | | |

### Approval

| Role | Name | Signature | Date |
|---|---|---|---|
| Author | {{AUTHOR}} | | |
| Reviewer (engineering) | | | |
| Approver ({{COMPANY}}) | | | |
| Approver ({{CLIENT}}) | | | |

---

## 1. Scope and references

### 1.1 Scope
This protocol covers acceptance testing of the control system for {{PROJECT_NAME}} at the works
of {{COMPANY}}, prior to despatch to site. Testing is performed on simulated field I/O.

**Not covered by this test.** Field device performance, actual process behaviour, and anything
that depends on real plant. Those belong to the SAT, and no result here should be read as
covering them.

### 1.2 References

| Ref | Document | Number | Rev |
|---|---|---|---|
| R1 | Functional Design Specification | | |
| R2 | I/O List | | |
| R3 | Cause and Effect Matrix | | |
| R4 | Bill of Materials | | |
| R5 | Panel general arrangement and schematics | | |

### 1.3 Attendees

| Name | Company | Role | Present for |
|---|---|---|---|
| | {{COMPANY}} | Test engineer | All |
| | {{CLIENT}} | Witness | |
| | | | |

---

## 2. Entry criteria

The FAT does not begin until every item below is true. Starting a FAT that is not ready wastes
the witness's time and produces a punch list that is really a build list.

| # | Criterion | Met | Initial |
|---|---|---|---|
| 1 | Panel build complete and inspected | | |
| 2 | Program written, compiled, and version recorded | | |
| 3 | HMI application complete, version recorded | | |
| 4 | Internal pre-FAT completed and faults cleared | | |
| 5 | Simulation rig available and proven | | |
| 6 | All reference documents at current revision and available | | |
| 7 | Test protocol issued to client at least 5 working days beforehand | | |
| 8 | Calibration certificates for test equipment in date | | |

**Pre-FAT.** Run the entire protocol yourself first. The witnessed FAT is a demonstration, not
a debugging session.

---

## 3. Test environment

### 3.1 Simulation method

| I/O type | Simulation method |
|---|---|
| Digital input | Switch box on terminals, one switch per point |
| Digital output | Indicator lamp or LED on terminals |
| Analog input | Signal generator, 4-20 mA, calibrated |
| Analog output | Loop calibrator in read mode |
| Safety input | Dual channel switch box, with fault injection capability |
| Network devices | Simulator or actual device where available |

### 3.2 Test equipment

| Equipment | Serial | Cal due | Used for |
|---|---|---|---|
| Loop calibrator | | | Analog I/O |
| Multimeter | | | Electrical checks |
| Insulation tester | | | Insulation resistance |

### 3.3 Software versions under test

| Item | Version | Checksum | Recorded by |
|---|---|---|---|
| PLC program | | | |
| HMI application | | | |
| Safety program | | | |

> Record the checksum, not just the version number. Two builds can share a version.

---

## 4. Documentation verification

| # | Check | Result | Initial |
|---|---|---|---|
| 4.1 | Schematics match the as-built panel | Pass / Fail | |
| 4.2 | BOM matches installed components, item by item | Pass / Fail | |
| 4.3 | Equipment manuals present | Pass / Fail | |
| 4.4 | Calibration certificates present and in date | Pass / Fail | |
| 4.5 | Software version documentation complete | Pass / Fail | |
| 4.6 | Spare parts list supplied | Pass / Fail | |
| 4.7 | CE / UKCA declaration prepared | Pass / Fail | |

---

## 5. Visual and mechanical inspection

| # | Check | Result | Initial |
|---|---|---|---|
| 5.1 | Enclosure undamaged, correct IP rating, seals intact | | |
| 5.2 | All components mounted securely | | |
| 5.3 | Wiring neat, ferruled, and identified per drawings | | |
| 5.4 | Terminal numbering matches schematics | | |
| 5.5 | Earth continuity, all metallic parts bonded | | |
| 5.6 | Segregation of power, control, instrument and data | | |
| 5.7 | Labels present, legible, and correct | | |
| 5.8 | Warning labels and arc flash label fitted | | |
| 5.9 | Door interlock on isolator operates | | |
| 5.10 | Gland plate drilled correctly, spare glands blanked | | |
| 5.11 | No swarf or debris in enclosure | | |

---

## 6. Power up and electrical tests

**Safety.** These tests involve live working. Follow the site electrical safety rules and
ensure a second competent person is present.

| # | Test | Expected | Measured | Result | Initial |
|---|---|---|---|---|---|
| 6.1 | Insulation resistance, power circuits, 500 V | > 1 MOhm | | | |
| 6.2 | Earth continuity, < 0.1 Ohm to earth bar | Pass | | | |
| 6.3 | Phase rotation | [L1 L2 L3] | | | |
| 6.4 | Supply voltage at isolator | [400 V ± 10%] | | | |
| 6.5 | 24 VDC supply voltage on load | 24 V ± 5% | | | |
| 6.6 | 24 VDC ripple | < 100 mV | | | |
| 6.7 | Protective device ratings match schematic | Pass | | | |
| 6.8 | Panel current draw | [expected A] | | | |

---

## 7. I/O verification

Every point on the I/O list is tested individually. This is the tedious part and it is the part
that saves the most time later: a crossed pair found here costs five minutes.

**Method, digital input.** Operate the switch. Confirm the correct tag changes state in the
controller, and that no other tag changes.

**Method, digital output.** Force the output from the controller. Confirm the correct lamp
lights and the terminal reads 24 V, and that no other output changes.

**Method, analog input.** Inject 4, 8, 12, 16 and 20 mA. Confirm engineering values match the
I/O list scaling at each point, within tolerance.

**Method, analog output.** Command 0, 25, 50, 75 and 100 percent. Confirm the loop calibrator
reads 4, 8, 12, 16 and 20 mA within tolerance.

| Tag | Address | Type | Injected | Expected | Observed | Pass | Initial |
|---|---|---|---|---|---|---|---|
| XV-101-ZSO | %I0.0 | DI | Closed | TRUE | | | |
| FT-101 | %IW64 | AI | 12 mA | 25.0 m3/h | | | |
| MTR-101-RUN | %Q0.0 | DO | Force ON | 24 V at X5:01 | | | |
| FCV-101 | %QW96 | AO | 50% | 12 mA | | | |

> Copy one row per point from the I/O list. A partial I/O check is not an I/O check.

### 7.1 Cross-talk check
| # | Test | Result |
|---|---|---|
| 7.1.1 | With each output forced individually, confirm no other output energises | |

---

## 8. Functional tests

Written directly from the FDS. Each test quotes the FDS section it proves, and the URS
requirement behind it.

| Test ref | FDS ref | URS ref | Description | Method | Expected result | Actual | Pass | Initial |
|---|---|---|---|---|---|---|---|---|
| FAT-FN-001 | 3 | URS-FN-001 | Mode selection | Select each mode at HMI | Mode changes and is indicated | | | |
| FAT-FN-002 | 4.1 | URS-FN-010 | Start sequence | Satisfy permissives, press Start | Steps execute in order per FDS 4.1 | | | |
| FAT-FN-003 | 4.1 | | Step timeout | Withhold step 2 transition | Alarm raised after timeout, sequence holds | | | |
| FAT-FN-004 | 4.3 | URS-FN-011 | Controlled stop | Press Stop mid cycle | Cycle completes then stops | | | |
| FAT-FN-005 | 4.5 | URS-FN-012 | Restart after power loss | Remove and restore supply | No automatic restart, manual reset required | | | |
| FAT-FN-006 | 7 | | Analog scaling | Inject range points | Values match RATS | | | |
| FAT-FN-007 | 8.3 | | Security levels | Attempt actions at each level | Only permitted actions available | | | |

---

## 9. Interlock and safety tests

Every row of the cause and effect matrix. Test the marks *and* confirm the blanks.

| Test ref | Cause ref | Cause simulated | Expected effects | Effects NOT expected | Actual | Pass | Initial |
|---|---|---|---|---|---|---|---|
| FAT-SF-001 | C-001 | E-stop station 1 pressed | All per C-001 row | | | | |
| FAT-SF-002 | C-002 | Guard door opened | Per C-002 row | FCV-101 does not close | | | |
| FAT-IL-001 | C-003 | LT-101 above 95% | Per C-003 row | | | | |

### 9.1 Safety function specific tests

| # | Test | Expected | Actual | Pass |
|---|---|---|---|---|
| 9.1.1 | Single channel fault, E-stop channel A | Safety function trips, fault annunciated | | |
| 9.1.2 | Single channel fault, E-stop channel B | Safety function trips, fault annunciated | | |
| 9.1.3 | Channel discrepancy time exceeded | Fault detected and latched | | |
| 9.1.4 | Reset with E-stop still pressed | Reset refused | | |
| 9.1.5 | Reset button held closed (welded contact) | Reset refused, requires falling edge | | |
| 9.1.6 | Safety response time | Within [ms] per calculation | | |

> Test 9.1.5 catches the most common reset circuit mistake. A reset that acts on level rather
> than edge will re-enable the machine the instant the guard closes if the button has stuck.

---

## 10. Alarm tests

| Test ref | Alarm | Trigger | Expected message | Priority correct | Ack works | Clears correctly | Pass |
|---|---|---|---|---|---|---|---|
| FAT-AL-001 | AL-003 | LT-101 above 95% | Per alarm list | | | | |

### 10.1 Alarm system behaviour
| # | Test | Expected | Pass |
|---|---|---|---|
| 10.1.1 | Alarm timestamp accuracy | Within 1 s of event | |
| 10.1.2 | Alarm ordering under simultaneous events | Chronological | |
| 10.1.3 | Acknowledgement records user and time | Recorded | |
| 10.1.4 | Alarm history survives power cycle | Retained | |

---

## 11. Communications tests

| # | Test | Expected | Actual | Pass |
|---|---|---|---|---|
| 11.1 | Link established to [peer] | Connected | | |
| 11.2 | Data exchange, all mapped points | Values match | | |
| 11.3 | Watchdog on link loss | Timeout detected within [s], defined action | | |
| 11.4 | Recovery on link restore | Automatic, no stale data | | |
| 11.5 | Network load under normal operation | < [%] | | |
| 11.6 | Unauthorised access attempt | Refused and logged | | |

---

## 12. Failure mode tests

| # | Failure injected | Expected response | Actual | Pass |
|---|---|---|---|---|
| 12.1 | Analog input open circuit | Below 3.6 mA detected, alarm, defined fail action | | |
| 12.2 | Analog input short circuit | Above 21 mA detected, alarm | | |
| 12.3 | Remote I/O disconnected | Comms alarm, outputs to defined state | | |
| 12.4 | 24 V supply removed | Outputs de-energise, orderly behaviour | | |
| 12.5 | CPU stopped | Outputs de-energise | | |
| 12.6 | HMI disconnected | Control continues, alarm raised | | |

---

## 13. Punch list

Items found during test. Category A must be closed before despatch. Category B may be closed
on site by agreement. Nothing ships with an open Category A.

| # | Category | Description | Raised by | Owner | Target date | Closed | Verified by |
|---|---|---|---|---|---|---|---|
| 1 | A / B | | | | | | |
| 2 | | | | | | | |

**Category A.** Prevents the system performing a specified function, or is a safety issue.
**Category B.** Cosmetic, documentation, or does not prevent the system being used.

---

## 14. Acceptance

### 14.1 Result summary

| Section | Tests | Passed | Failed | Not tested |
|---|---|---|---|---|
| 4 Documentation | | | | |
| 5 Visual | | | | |
| 6 Electrical | | | | |
| 7 I/O | | | | |
| 8 Functional | | | | |
| 9 Safety | | | | |
| 10 Alarms | | | | |
| 11 Communications | | | | |
| 12 Failure modes | | | | |

### 14.2 Recommendation

- [ ] **Accepted.** System may be despatched.
- [ ] **Accepted with punch list.** Category B items only, agreed for site closure.
- [ ] **Not accepted.** Retest required. Reason: ______________________________

### 14.3 Signatures

| Role | Name | Company | Signature | Date |
|---|---|---|---|---|
| Test engineer | | {{COMPANY}} | | |
| Quality | | {{COMPANY}} | | |
| Witness | | {{CLIENT}} | | |
| Project manager | | {{CLIENT}} | | |