Testing

Site Acceptance Test Protocol

SAT

The SAT proves what the FAT could not: that the field devices are wired to the right terminals, that the loops read correctly end to end, and that the process behaves as the control narrative says it will. It is also the point at which the client formally takes the system on.

Do you need this one?

Every installation. Where a FAT was witnessed, the SAT can reference it and avoid repeating bench tests, but the loop checks and the process tests cannot be skipped.

What is in it

  1. 01Scope and reference to FAT
  2. 02Entry criteria and site readiness
  3. 03Installation inspection
  4. 04Loop checks, end to end
  5. 05Field device calibration
  6. 06Functional tests on real plant
  7. 07Safety validation
  8. 08Performance and capacity tests
  9. 09Training record
  10. 10Punch list
  11. 11Handover and acceptance

Written by

Commissioning engineer

Approved by

Client, formal handover

Written against

  • IEC 62381

Preview

SAT-Protocol.md
# Site Acceptance Test Protocol
## {{PROJECT_NAME}}

| | |
|---|---|
| **Document title** | Site Acceptance Test Protocol (SAT) |
| **Document number** | {{DOC_NO}} |
| **Revision** | {{REV}} |
| **Date** | {{DATE}} |
| **Project** | {{PROJECT_NAME}} |
| **Client** | {{CLIENT}} |
| **Prepared by** | {{AUTHOR}}, {{COMPANY}} |

### Revision history

| Rev | Date | Description | Author | Approved |
|---|---|---|---|---|
| 0 | {{DATE}} | First issue | {{AUTHOR}} | |
| | | | | |

### Approval

| Role | Name | Signature | Date |
|---|---|---|---|
| Author | {{AUTHOR}} | | |
| Reviewer (engineering) | | | |
| Approver ({{COMPANY}}) | | | |
| Approver ({{CLIENT}}) | | | |

---

## 1. Scope

Acceptance testing of the control system for {{PROJECT_NAME}} installed at {{CLIENT}}, on real
plant with real field devices.

### 1.1 Relationship to the FAT
Tests passed and witnessed at FAT are not repeated in full. What must be repeated is anything
that depends on the physical installation: every loop check, every safety function, and every
test whose FAT result relied on simulation.

| FAT reference | Date | Result | Punch items outstanding |
|---|---|---|---|
| | | | |

---

## 2. Entry criteria

| # | Criterion | Met | Initial |
|---|---|---|---|
| 1 | Installation complete, cables landed and glanded | | |
| 2 | Cable tests complete, results available | | |
| 3 | Field devices installed and accessible | | |
| 4 | Power available and stable | | |
| 5 | Compressed air and utilities available | | |
| 6 | Mechanical completion signed off | | |
| 7 | FAT punch list Category A items closed | | |
| 8 | Permit to work arrangements in place | | |
| 9 | Plant available for testing, and isolated where required | | |
| 10 | Operations staff available for training | | |

---

## 3. Installation inspection

| # | Check | Result | Initial |
|---|---|---|---|
| 3.1 | Panel installed level, secure, accessible | | |
| 3.2 | Cable entries correct, glands tight, IP maintained | | |
| 3.3 | Earthing installed per drawing, continuity verified | | |
| 3.4 | Screens earthed at one end only, per cable schedule | | |
| 3.5 | Segregation maintained in tray and trunking | | |
| 3.6 | Field devices installed per manufacturer instructions | | |
| 3.7 | Instrument installation correct: impulse lines, orientation, isolation | | |
| 3.8 | Labels fitted at both ends of every cable | | |
| 3.9 | Panel free from site debris | | |

---

## 4. Loop checks

The core of the SAT. Every signal is proved from the field device to the operator screen. A
loop check that stops at the panel terminal is a terminal check.

**Method, discrete.** Operate the device in the field. Confirm the state changes at the
controller and on the HMI, with correct description.

**Method, analog.** Apply a known input at the device, or use the device's own simulation.
Confirm the value at the controller and on the HMI at 0, 50 and 100 percent.

| Tag | Description | Field operated | Controller reads | HMI shows | Correct description | Pass | Tester | Date |
|---|---|---|---|---|---|---|---|---|
| XV-101-ZSO | Inlet valve open limit | | | | | | | |
| FT-101 | Feed flow | | | | | | | |
| MTR-101-RUN | Feed pump run | | | | | | | |
| FCV-101 | Feed control valve | | | | | | | |

### 4.1 Valve and actuator strokes
| Tag | Command | Observed travel | Time to stroke | Limit switches | Fail position verified | Pass |
|---|---|---|---|---|---|---|
| FCV-101 | 0, 50, 100% | | | | Air removed, valve closes | |
| XV-101 | Open / close | | | | | |

---

## 5. Field device calibration

| Tag | Type | As found | As left | Tolerance | Cert no | Calibrated by | Date |
|---|---|---|---|---|---|---|---|
| FT-101 | Flow | | | ± [%] | | | |
| LT-101 | Level | | | | | | |
| TT-101 | Temperature | | | | | | |

Record as found values before adjusting. An instrument that was out of tolerance on arrival is
information the site needs.

---

## 6. Functional tests on plant

| Test ref | FDS ref | Description | Expected | Actual | Pass | Initial |
|---|---|---|---|---|---|---|
| SAT-FN-001 | 3 | Mode selection on plant | | | | |
| SAT-FN-002 | 4.1 | Full start sequence with real equipment | | | | |
| SAT-FN-003 | 4.2 | Steady state running for [duration] | | | | |
| SAT-FN-004 | 4.3 | Controlled stop | | | | |
| SAT-FN-005 | 4.4 | Emergency stop, real | | | | |
| SAT-FN-006 | 4.5 | Restart after power interruption | | | | |
| SAT-FN-007 | 9 | Recipe download and execution | | | | |

---

## 7. Safety validation

Every safety function is validated on the installed system. This is not a repeat of the FAT: it
proves the real device, the real wiring and the real stopping performance.

| # | Safety function | Test | Expected | Actual | Pass | Witness |
|---|---|---|---|---|---|---|
| 7.1 | E-stop station 1 | Press | Category [0/1] stop, all motion ceases | | | |
| 7.2 | E-stop station 2 | Press | As above | | | |
| 7.3 | Guard interlock | Open during motion | Motion stops within [ms] | | | |
| 7.4 | Guard interlock | Attempt start with guard open | Start refused | | | |
| 7.5 | Reset | Reset with hazard present | Reset refused | | | |
| 7.6 | Stopping time measurement | Measure with instrument | Within calculated safety distance | | | |
| 7.7 | Muting / bypass (if fitted) | Verify conditions and annunciation | Per design | | | |

**Stopping time.** Measure it, do not assume it. The safety distance calculation to ISO 13855
depends on the real stopping time of the real machine with its real load.

---

## 8. Performance and capacity

| # | Measure | Target | Achieved | Pass |
|---|---|---|---|---|
| 8.1 | Throughput | [units/h] | | |
| 8.2 | Cycle time | [s] | | |
| 8.3 | Controller scan time | < [ms] | | |
| 8.4 | Controller memory used | < [%] | | |
| 8.5 | Spare I/O available | > 20% | | |
| 8.6 | Network utilisation | < [%] | | |
| 8.7 | Alarm rate, average per hour | < 6 | | |
| 8.8 | HMI screen call up time | < [s] | | |

---

## 9. Training

| Course | Attendees | Duration | Delivered by | Date | Materials issued |
|---|---|---|---|---|---|
| Operation | | | | | |
| Alarm response | | | | | |
| Maintenance and fault finding | | | | | |
| Engineering, program access | | | | | |

| Name | Role | Signature | Date |
|---|---|---|---|
| | | | |

---

## 10. Punch list

| # | Category | Description | Raised by | Owner | Target | Closed | Verified |
|---|---|---|---|---|---|---|---|
| 1 | A / B | | | | | | |

---

## 11. Handover and acceptance

### 11.1 Deliverables received

| # | Item | Received | Initial |
|---|---|---|---|
| 1 | As-built schematics | | |
| 2 | Final I/O list | | |
| 3 | Program source and backup | | |
| 4 | HMI application backup | | |
| 5 | Software version record | | |
| 6 | O&M manual | | |
| 7 | Spare parts | | |
| 8 | Calibration certificates | | |
| 9 | Declaration of conformity | | |
| 10 | Training records | | |

### 11.2 Acceptance

- [ ] **Accepted.** System taken over by {{CLIENT}} on the date below.
- [ ] **Accepted with punch list.** Items listed in section 10, owners and dates agreed.
- [ ] **Not accepted.** Reason: ______________________________

### 11.3 Signatures

| Role | Name | Company | Signature | Date |
|---|---|---|---|---|
| Commissioning engineer | | {{COMPANY}} | | |
| Project manager | | {{COMPANY}} | | |
| Client engineering | | {{CLIENT}} | | |
| Client operations | | {{CLIENT}} | | |

### 11.4 Warranty
Warranty period begins on the acceptance date above and runs for [period]. Scope and exclusions
per contract clause [ref].