The FDS is the contract between what was asked for and what gets built. It takes each requirement from the URS and says, concretely, how the control system satisfies it: which modes exist, what each sequence step does, what every alarm means, what happens on power loss. If the FAT is going to be arguable, it is because this document was vague.

Do you need this one?

Every project. This is the one document worth writing even when nobody has asked for it, because it is what you will read in eighteen months when something needs changing and nobody remembers why the interlock is there.

What is in it

  1. 01Purpose and references
  2. 02System architecture
  3. 03Operating modes
  4. 04Sequence of operation
  5. 05Interlocks and permissives
  6. 06Alarms
  7. 07Analog handling and scaling
  8. 08Operator interface
  9. 09Data, recipes and reporting
  10. 10Communications
  11. 11Failure behaviour
  12. 12Software structure
  13. 13Requirement traceability

Written by

Control systems engineer

Approved by

Client engineering, and process owner

Written against

  • IEC 61131-3
  • ISA-88 for batch and sequence structure
  • ISA-18.2 for alarms

Preview

FDS.md
# Functional Design Specification
## {{PROJECT_NAME}}

| | |
|---|---|
| **Document title** | Functional Design Specification (FDS) |
| **Document number** | {{DOC_NO}} |
| **Revision** | {{REV}} |
| **Date** | {{DATE}} |
| **Project** | {{PROJECT_NAME}} |
| **Client** | {{CLIENT}} |
| **Prepared by** | {{AUTHOR}}, {{COMPANY}} |

### Revision history

| Rev | Date | Description | Author | Approved |
|---|---|---|---|---|
| 0 | {{DATE}} | First issue | {{AUTHOR}} | |
| | | | | |

### Approval

| Role | Name | Signature | Date |
|---|---|---|---|
| Author | {{AUTHOR}} | | |
| Reviewer (engineering) | | | |
| Approver ({{COMPANY}}) | | | |
| Approver ({{CLIENT}}) | | | |

---

## 1. Purpose and references

### 1.1 Purpose
This document describes how the control system for {{PROJECT_NAME}} satisfies the requirements
of the User Requirement Specification. It is written to be sufficient for a competent control
engineer to implement the system without further clarification, and for the FAT to be written
directly from it.

### 1.2 Reference documents

| Ref | Document | Number | Rev |
|---|---|---|---|
| R1 | User Requirement Specification | | |
| R2 | P&ID / General arrangement | | |
| R3 | I/O list | | |
| R4 | Cause and effect matrix | | |
| R5 | Risk assessment | | |

### 1.3 Standards
IEC 61131-3 for programming languages. ISA-88 for sequence and state model terminology.
ISA-18.2 for alarm management. IEC 60204-1 for electrical equipment of machines.

---

## 2. System architecture

### 2.1 Overview
[Describe the topology: controllers, remote I/O, drives, HMI, network segments.]

### 2.2 Hardware summary

| Item | Manufacturer | Model | Qty | Location |
|---|---|---|---|---|
| PLC CPU | | | | |
| Remote I/O | | | | |
| HMI | | | | |
| Safety controller | | | | |
| Managed switch | | | | |

### 2.3 Networks

| Network | Protocol | Media | Address range | Devices |
|---|---|---|---|---|
| Control | [EtherNet/IP, PROFINET] | | | |
| Safety | [CIP Safety, PROFIsafe] | | | |
| Plant | [OPC UA] | | | |

### 2.4 Software versions

| Item | Software | Version | Notes |
|---|---|---|---|
| PLC program | | | |
| HMI application | | | |
| Firmware, CPU | | | |

> Record exact versions. "Latest" is not a version, and at SAT it is the difference between
> a five minute check and an afternoon.

---

## 3. Operating modes

| Mode | Entry condition | Behaviour | Exit condition |
|---|---|---|---|
| Off | Power applied, no start | Outputs de-energised, no motion | Start selected |
| Manual | Selected at HMI, guards closed | Individual devices operable, interlocks active | Mode change |
| Auto | Selected, ready conditions met | Full sequence runs | Stop, fault, or mode change |
| Maintenance | Key switch, authorised user | [Reduced speed / bypass, define exactly what is bypassed] | Key removed |

**Mode change rules.** [State when a mode change is permitted and what happens to a running
sequence when it occurs. This is where the difference between an orderly stop and a mess lives.]

---

## 4. Sequence of operation

Written as numbered steps with an explicit transition condition. A step with no stated
transition is a step that can hang, and that is what an operator will report as "it stopped
and nothing happened".

### 4.1 Start sequence

| Step | Action | Transition to next step | Timeout | On timeout |
|---|---|---|---|---|
| 1 | [Action] | [Condition] | [s] | [Alarm ref, and behaviour] |
| 2 | | | | |
| 3 | | | | |

### 4.2 Normal running
[Describe steady state behaviour, cycle timing, and how throughput is regulated.]

### 4.3 Controlled stop
| Step | Action | Transition | Timeout |
|---|---|---|---|
| 1 | Complete current cycle | Cycle complete flag | [s] |
| 2 | [Action] | | |

### 4.4 Emergency stop
[Category 0 or 1 per IEC 60204-1. State which, and state exactly what remains energised.]

### 4.5 Recovery and restart
[What the operator must do after a fault or an E-stop. State whether a manual reset is required
before motion is possible, because the safety assessment almost certainly requires one.]

---

## 5. Interlocks and permissives

A **permissive** must be true to start. An **interlock** stops or prevents operation when it
goes false. They are not the same thing and confusing them produces machines that cannot be
restarted after a trip.

| Ref | Type | Condition | Affects | Action | Reset |
|---|---|---|---|---|---|
| INT-001 | Interlock | [Signal false] | [Device] | [Immediate stop] | [Auto / manual] |
| PRM-001 | Permissive | [Condition] | [Sequence] | [Prevents start] | n/a |

---

## 6. Alarms

Per ISA-18.2: every alarm requires a defined operator response. An indication that needs no
response is a status, not an alarm, and putting it in the alarm list is how alarm floods start.

| Tag | Description | Priority | Trip | Delay | Operator action | Auto reset |
|---|---|---|---|---|---|---|
| AL-001 | | High | | [s] | [What the operator does] | No |
| AL-002 | | Medium | | | | |

**Priority definitions.** High: immediate action required to avoid injury, damage or product
loss. Medium: action required this shift. Low: action required, not time critical.

---

## 7. Analog handling and scaling

| Tag | Signal | Raw range | Engineering range | Units | Filter | Fault action |
|---|---|---|---|---|---|---|
| | 4-20 mA | 0-27648 | | | [s] | [Hold / fail safe value] |

**Out of range.** [State the behaviour below 3.6 mA and above 21 mA. A broken wire reads as
zero flow, and if that is not detected the sequence will happily continue.]

---

## 8. Operator interface

### 8.1 Screen hierarchy
[List screens and navigation.]

### 8.2 Common conventions

| Element | Convention |
|---|---|
| Running | [Colour and shape] |
| Stopped | |
| Faulted | |
| Unacknowledged alarm | |

> Colour alone must not carry meaning. Use shape or text as well, for colour vision deficiency
> and for the fact that panel screens fade.

### 8.3 Security levels

| Level | Who | Permitted |
|---|---|---|
| 0 | Anyone | View only |
| 1 | Operator | Start, stop, acknowledge |
| 2 | Supervisor | Setpoint changes within limits |
| 3 | Engineer | Full, including bypasses |

---

## 9. Data, recipes and reporting

### 9.1 Recipe structure
| Parameter | Type | Range | Default | Units | Security level |
|---|---|---|---|---|---|

### 9.2 Records
| Record | Trigger | Fields | Retention | Format |
|---|---|---|---|---|

---

## 10. Communications

| Link | Peer | Protocol | Rate | Data exchanged | Failure behaviour |
|---|---|---|---|---|---|

**Watchdog.** [State the timeout and what happens when it expires. A comms link with no
watchdog will one day deliver a stale value that looks perfectly valid.]

---

## 11. Failure behaviour

| Failure | Detection | System response | Alarm | Recovery |
|---|---|---|---|---|
| Power loss | | Outputs de-energise | | [Manual restart required?] |
| CPU fault | | | | |
| Remote I/O comms loss | | | | |
| Sensor out of range | | | | |
| Drive fault | | | | |

---

## 12. Software structure

### 12.1 Program organisation

| POU | Language | Purpose | Scan |
|---|---|---|---|
| Main | LD | Coordination | Cyclic |
| | | | |

### 12.2 Naming conventions
[State the tag naming rule and stick to it. Include an example of each type.]

### 12.3 Memory map
| Area | Range | Use |
|---|---|---|

---

## 13. Requirement traceability

| URS ref | FDS section | Implemented in | Test ref |
|---|---|---|---|
| URS-OP-001 | | | |

Travels with