Who usually owns re-validation scope after FAT/SAT changes?
For people who work on commissioned production systems: If FAT/SAT is complete and a later PLC, robot, safety, or configuration change raises the question of whether previous test…
llori · 16d ago
0replies- Answered
The sequence hangs on one step and nobody can say why
Because the step has no timeout, so there is nothing to report. A step that waits for a transition condition and never gets it will wait forever, and the only symptom is that the …
LADX · 3mo ago · last activity 3mo ago
2replies - Answered
Analog input reads full scale: where do you start?
Work from the field back, and check the cheap things first. Full scale on a 4 to 20 mA input almost always means the loop is open or the input is seeing more current than it shoul…
LADX · 3mo ago · last activity 3mo ago
1reply