Handover

Handover and As-Built Pack

HO

The handover pack is the permanent record. Years after the project team has moved on, this is what the site has. Its completeness decides whether the next modification takes an afternoon or a fortnight of reverse engineering.

Do you need this one?

Every project, at completion. Build it as you go rather than at the end, because assembling it retrospectively is when you discover the as-builts were never marked up.

What is in it

  1. 01Document register
  2. 02Software and firmware record
  3. 03Backup and restore procedure
  4. 04Spare parts
  5. 05Maintenance schedule
  6. 06Support and escalation
  7. 07Receipt

Written by

Project engineer

Approved by

Client, on acceptance

Preview

Handover-Pack.md
# Handover and As-Built Pack
## {{PROJECT_NAME}}

| | |
|---|---|
| **Document title** | Handover and As-Built Pack (HO) |
| **Document number** | {{DOC_NO}} |
| **Revision** | {{REV}} |
| **Date** | {{DATE}} |
| **Project** | {{PROJECT_NAME}} |
| **Client** | {{CLIENT}} |
| **Prepared by** | {{AUTHOR}}, {{COMPANY}} |

### Revision history

| Rev | Date | Description | Author | Approved |
|---|---|---|---|---|
| 0 | {{DATE}} | First issue | {{AUTHOR}} | |
| | | | | |

### Approval

| Role | Name | Signature | Date |
|---|---|---|---|
| Author | {{AUTHOR}} | | |
| Reviewer (engineering) | | | |
| Approver ({{COMPANY}}) | | | |
| Approver ({{CLIENT}}) | | | |

---

## 1. Document register

Every document handed over, at the revision handed over. "Latest" is not a revision.

| # | Document | Number | Rev | Format | Location | Received |
|---|---|---|---|---|---|---|
| 1 | User Requirement Specification | | | PDF | | |
| 2 | Functional Design Specification | | | PDF | | |
| 3 | Software Design Specification | | | PDF | | |
| 4 | Control narrative | | | PDF | | |
| 5 | I/O list, as-built | | | XLSX | | |
| 6 | Cause and effect matrix | | | XLSX | | |
| 7 | RATS | | | XLSX | | |
| 8 | Alarm list, rationalised | | | XLSX | | |
| 9 | Panel schematics, as-built | | | PDF + DWG | | |
| 10 | Panel general arrangement | | | PDF + DWG | | |
| 11 | Cable schedule, as-built | | | XLSX | | |
| 12 | Loop drawings | | | PDF | | |
| 13 | Bill of materials | | | XLSX | | |
| 14 | Risk assessment | | | PDF | | |
| 15 | Safety calculations | | | PDF | | |
| 16 | FAT protocol and results | | | PDF | | |
| 17 | SAT protocol and results | | | PDF | | |
| 18 | Commissioning checklist, completed | | | PDF | | |
| 19 | Calibration certificates | | | PDF | | |
| 20 | O&M manual | | | PDF | | |
| 21 | Training records | | | PDF | | |
| 22 | Declaration of conformity | | | PDF | | |
| 23 | Equipment manuals, all devices | | | PDF | | |

**As-built means as-built.** If a wire was moved during commissioning and the drawing was not
updated, the pack is wrong and the next person will trust it.

---

## 2. Software and firmware record

| Item | Product | Version | Checksum | Licence key held by | Media |
|---|---|---|---|---|---|
| PLC program | | | | | |
| Safety program | | | | | |
| HMI application | | | | | |
| CPU firmware | | | | | |
| Remote I/O firmware | | | | | |
| Drive parameters | | | | | |
| Managed switch config | | | | | |
| Programming software | | | | | |

**Licences.** State who holds them and whether the site can open the program without buying
software. A program the site cannot open is a program the site does not own.

---

## 3. Backup and restore

### 3.1 What is backed up
| Item | Location | Frequency | Responsible |
|---|---|---|---|
| PLC program | | On change | |
| HMI application | | On change | |
| Recipes and parameters | | Weekly | |
| Historical data | | Daily | |

### 3.2 Restore procedure
[Numbered steps to restore a failed controller from backup, including how to verify the restore
worked. Write it so that someone who has never done it can follow it at 2 am.]

1. [Step]
2. [Step]

**Restore has been tested.** Date: __________ By: __________

> An untested backup is a hope. Test the restore before handover and record it here.

---

## 4. Spare parts

| Item | Manufacturer | Part number | Qty supplied | Qty recommended | Location | Lead time |
|---|---|---|---|---|---|---|
| | | | | | | |

**Critical spares.** [Items with a lead time long enough to matter. These are the ones worth
holding, and the ones the site will not think about until one fails.]

---

## 5. Maintenance schedule

| Task | Interval | Duration | Skill | Procedure ref |
|---|---|---|---|---|
| Panel inspection, thermal check | 6 months | 1 h | Electrician | |
| Filter fan replacement | 12 months | 30 min | Technician | |
| Instrument calibration | 12 months | | Instrument tech | |
| Safety function proof test | 12 months | | Competent person | |
| Backup verification | 6 months | 1 h | Engineer | |
| UPS battery test | 12 months | | Electrician | |

**Safety proof testing.** The interval comes from the safety calculation, not from convenience.
Record it and hold to it, because the achieved PL assumes it.

---

## 6. Support and escalation

| Level | Contact | Hours | Response | Covers |
|---|---|---|---|---|
| 1 | Site maintenance | | | First line |
| 2 | {{COMPANY}} support | | | Program and configuration |
| 3 | Vendor | | | Hardware failure |

| Detail | Value |
|---|---|
| Support contract reference | |
| Warranty expiry | |
| Remote access method | |
| Remote access approval process | |

---

## 7. Receipt

The items listed in section 1 have been received by {{CLIENT}}.

| Role | Name | Signature | Date |
|---|---|---|---|
| Issued by | | | |
| Received by | | | |